Anomaly, cause unknownStatus not statedOperation Hidden Strain (field report, 18 Nov 2026)

PJM / AEP: Two post-contingency voltage warnings (maintain 127.0 kV at a 138 kV bus) in AEP...

PJM / AEP · PJM AEP zone

Local voltage contingency exposure.

How confirmed
confirmed
First reported
Nov 16, 11:19 UTC
Last updated
Nov 18, 00:00 UTC
Sector
Electricity
Condition
elevated stress
Systems
Sub-transmission voltage
Redundancy used
None available per posting
Remaining resilience
Low locally.
Duration
Unknown (no end time shown)
Corroboration
Single primary source.
Six dimensions
service availability: normal; operating conditions: constrained; redundancy: none; remaining capacity: thin; recovery quality: unknown; compounding exposure: low

Known impact

None reported.

Recovery

Unknown

Timeline

  • Nov 16, 11:19 UTC: Started
  • Nov 18, 23:59 UTC: First public report
  • Nov 18, 00:00 UTC: Open on report date

Sources

  • PJM Interconnection · Nov 18, 00:00 UTC: PJM Emergency Procedures postings board (Nov 16 to 18, 2026)

Not yet known

  • End time and cause.

Operation Hidden Strain (field report, 18 Nov 2026). Historical baseline, not live data. State shown is as of the report date.